Which are the most important tasks for project planning? finishing up old projects, scheduling meetings, and updating spreadsheets assigning resources to tasks, creating a timeline, and making a budget updating the schedule, adjusting the budget, and communicating with the team assessing the final project, prioritizing tasks, and distributing resources

Respuesta :

I would say the correct answer is assigning resources to tasks, creating a timeline, and making a budget.
When you are planning a project, obviously the most important thing is to create a timeline of how you want that project to go. In order to do this, you also need to have a certain budget so as to pay for everything you want to do within your project.

Answer:

b

Explanation: