contestada

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.

WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements 67 43 63
On-hand 46
Net requirements
Planned order receipt
Planned order release