Which of these approaches will NOT accelerate the completion of a project?A. Improve the working method.B. Increase the bureaucratic oversight.C. Improve the productivity of existing project resources.D. Increase the quantity of personnel and equipment.

Respuesta :

Answer:

B. Increase the bureaucratic oversight

Explanation:

In the cash when the project is finished earlier at the time where there is a large number of resources i.e. deployed also at that time the new methods are applied so that the work could be done in fastest way due to which the productivity of the present resources could be rised.

So here according to the given options, the Option B is correct as it does not accelerate the project completion

The same is to be considered