The project has been challenging to manage. Everyone has been on edge due to pressure to complete the project on time. Unfortunately, the tension has grown to the point where team meetings have become shouting matches and little work is accomplished during the meetings. One team member asks to be excused from future team meetings, as all the shouting upsets him. Meanwhile, the sponsor has asked to attend team meetings in order to better understand how the project is going and the issues involved in completing the project, and the customer has started discussions about adding scope to the project. In this situation, it would be BEST for the project manager to:

Respuesta :

Answer: C. Involve the team in creating ground rules for the meetings.

Explanation:

The meetings have seemingly descended into anarchy and as such needs to be controlled in an orderly manner to make any sort of progress. One way this can be done is through the setting of ground rules. These rules need to be accepted and inclusive of people's qualms or else the arguments will continue.

When the rules are made therefore, the inputs of the entire team should be taken into consideration and this is what the Project manager needs to do. Setting all inclusive rules also helps the team understand each other better during the discussions are point of views will be seen and understood better.

Q&A Education