Answer:
$91 favorable
Explanation:
Variable overhead rate variance = (Standard variable overhead rate - Actual variable overhead rate) * Actual hour worked
Therefore, we have:
Variable overhead rate variance = ($8.00 - $7.90) * 910 = $91 favorable
Note: the variable overhead rate variance is said to be favorable becasue standard variable overhead rate is geater than the actual variable overhead rate.