Respuesta :
Answer:
The cost per equivalent unit for conversion costs for January in the Molding Department is closest to $9.94
Explanation:
The concept of Equivalent Units of Production focus on the output in terms of percentage of completion in the inputs in that process.
Calculation of Total Conversion cost for the Molding Department for January
Beginning Work In Process Inventory $34,558
Incurred during the year $559,254
Total Conversion cost $593812
Calculation of Total Equivalent Units for the Molding Department for January
Ending work in process inventory 7,300× 40 % 2920
Completed and transferred 56,800× 100% 56800
Total Equivalent Units 59,720
Calculation of Cost per equivalent unit
Cost per equivalent unit = Total Conversion cost $593812 /Total Equivalent Units 59,720 = 9.94 (2 d.p)