Answer:
3. MOH allocated to job= predetermined MOH rate * actual amount of allocation base used by the job
Explanation:
3. MOH allocated to job= predetermined MOH rate * actual amount of allocation base used by the job
The predetermined overhead rate is used to apply manufacturing overhead costs to production jobs. the quantity of a cost driver required by a particular job is multiplied by a predetermined overhead rate to determine the amount of overhead cost applied to the job.
An estimate is made of
Predetermined Overhead Rate= Budgeted Manufacturing Overhead Cost/ Budgeted amount of cost driver
The predetermined overhead rate is used to apply manufacturing overhead costs to production jobs. The quantity of the cost driver ( or activity base ) required by a particular job is multiplied by the predetermined overhead rate to determine the amount of overhead cost applied to the job.