Claire is a manager at a toy packaging company. The company packs 80 boxes of toys every hour for the first 3 hours of the day. They stop packaging for the next 2 hours in order to carry out a training session. Then, for the next 4 hours, they pack 20 boxes of toys every hour. Which graph models the piecewise function for the given situation?

Respuesta :

Answer:

See the attached figure.

Step-by-step explanation:

Modeling each part as a function.

Let x is hours of the working day

The company packs 80 boxes of toys every hour for the first 3 hours of the day. ⇒ y₁ = 80 x , x ∈ [0,3]

At the end of the 3 hours The company packs = 80 * 3 = 240

They stop packaging for the next 2 hours in order to carry out a training session. ⇒ y₂ = 240 , x ∈ [3,5]

Then, for the next 4 hours, they pack 20 boxes of toys every hour

y₃ = 20x + c , x ∈ [5,9]

To find c, y₂ = y₃ at x =5

∴ 240 = 20 * 5 + c

∴ c = 240 - 20 * 5 =240 - 100 = 140

∴ y₃ = 20x + 140 , x ∈ [5,9]

So,

y₁ = 80 x , x ∈ [0,3]

y₂ = 240 , x ∈ [3,5]

y₃ = 20x + 140 , x ∈ [5,9]

The graph models the piecewise function for the given situation is as shown in the attached figure.

Ver imagen Matheng

Answer:

c

Step-by-step explanation:

see attachment

Ver imagen paigekosineki