Which of the following is NOT a valid principle of bottleneck​ management? A. Increasing the capacity of a​ non-bottleneck station increases the capacity for the whole system. B. Release work orders to the system at the pace set by the​ bottleneck's capacity. C. Increasing the capacity of a​ non-bottleneck station is a mirage. D. Lost time at the bottleneck represents lost capacity for the whole system.

Respuesta :

Answer:

option A  .

Explanation:

The correct answer is option A  .

A bottleneck is a process in a chain process which limits the capacity of the capacity of the whole chain.        

bottleneck is the event which occur commonly in the manufacturing companies.                    

A bottleneck process occur when the input comes faster than the output of the next step.                

so, increasing the capacity of non bottleneck station will not decide the station capacity.