Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.r: 10.00%Year 0 1 2 3Cash flows −$1,050 $450 $460 $470a. $92.37b. $96.99c. $101.84d. $106.93e. $112.28