Answer:
Estimated manufacturing overhead rate= $69 per machine hour.
Explanation:
Giving the following information:
Aaron allocates overhead costs based on machine hours. The estimated machine hours for the coming year are 8,000 hours. Manufacturing overhead costs for the coming year are $ 550,000.
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base= 550000/8000= $69 per machine hour.