Answer:
Total cost= $2467
Explanation:
Giving the following information:
The Assembly Department uses a departmental overhead rate of $ 60 per machine hour.
The Sanding Department uses a departmental overhead rate of $ 20 per direct labor hour
Direct labor hours used
Assembly Department - 8
Sanding Department - 5
Machine hours used
Assembly Department - 10
Sanding Department - 7
The cost for direct labor is $32 per direct labor hour and the cost of the direct materials used by Job 603 is $1351.
Total cost= direct material + direct labor + MOH
Total cost= 1351 + (13*32) + (60*10 + 20*5)= $2467