contestada

Consider the following work breakdown structure:
Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A, B,C - - -
A D 38 50 62
B E 90 99 108
C End 85 100 115
D F 19 25 31
E End 91 100 115
F End 62 65 68
What is the estimated expected (mean) time for project completion?

Respuesta :

Answer:

The estimated expected (mean) time for project completion is 440 hours.

Explanation:

The given breakdown structure is

Activity         Precedes         Optimistic       Most Likely         Pessimistic  

A                         D                      38                      50                      62  

B                         E                      90                      99                      108  

C                         End                  85                      100                    115  

D                         F                       19                       25                      31  

E                         End                   91                      100                     115  

F                         End                   62                      65                      68

Using the table we get

[tex]\sum t_0=38+90+85+19+91+62=385[/tex]

[tex]\sum t_m=50+99+100+25+100+65=439[/tex]

[tex]\sum t_p=62+108+115+31+115+68=499[/tex]

The formula for estimated expected (mean) time for project completion is

[tex]t=\frac{\sum t_0+4\cdot \sum t_m+\sum t_p}{6}[/tex]

[tex]t=\frac{385+4\cdot 439+499}{6}[/tex]

[tex]t=440[/tex]

Therefore the estimated expected (mean) time for project completion is 440 hours.