Respuesta :
Answer
Tyler to do the job alone =18/1 = 18 hrs
Solution
It takes Tyler twice as long as Kyle to complete the same job.
efficiency of Kyle is twice the efficiency of Tyler
Let x be the efficiency of Tyler the efficiency of Kyle is 2x
efficiency of Tyler : efficiency of Tyler = x :2x =1:2
Therefore total efficiency = 1 + 2 =3x
The total job = efficiency x total time
Here total time to complete the job=6 hrs
Total job =18
Time taken to complete the job =Total job/efficiency
Tyler to do the job alone =18/1 = 18 hrs
Kyle to do the job alone =18/2 = 9 hrs
Answer: Time taken by Tyler to do the job alone =18 days.
Explanation:
Since we have given that
Tyler takes twice as long as Kyle to complete the same job,
Let the work done by Kyle in 1 day be
[tex]\frac{1}{x}[/tex]
Let the work done by Tyler in 1 day
[tex]\frac{1}{2x}[/tex]
If the men work together , they can complete the work in 6 hours.
According to question, we get
[tex]\frac{1}{x}+\frac{1}{2x}=\frac{1}{6}\\\\\implies \frac{2+1}{2x}=\frac{1}{6}\\\\\implies \frac{3}{2x}=\frac{1}{6}\\\\\implies x=9[/tex]
Hence, time taken by Kyle is x= 9 hours
and
Time taken by Tyler to do the job alone is given by
[tex]2x=2\times 9=18\ hours[/tex]