In project management, PERT typically relies on the assumption that individual activity completion times follow a beta distribution. However, the overall PERT critical path time is assumed to follow a normal distribution because of the:

1. Method of successive approximation
2. Binomial theorem
3. Theory of constraints
4. Central limit theorem