Why is the critical path critical?
1) The tasks on the critical path are the most important ones for achieving the project goal.
2) Any delay in the critical path delays the project completion.
3) The critical path determines the shortest possible duration for completing the project.
4) The critical path includes all the tasks that require the most resources.