- A professor has been contacted by four not-for-profit agencies that
are willing
to work with student consulting teams. The agencies
need
help with such things as budgeting, information systems,
coordinating volunteers, and forecasting. Although each of the four
student
teams could work with any of the agencies, the professor
feels that there
is a difference in the amount of time it would take
each group to solve each problem. The professor's estimate of the
time, in days,
is given in the table below. Formulate this problem as a
linear
programming model to determine which team works with
which
project. You do not need to solve the model. (10 points)
Projects
Team Budgeting Information Volunteers Forecasting
A
32
35
15
27
B
38
40
18
35
C
41
42
25
38
D
45
45
30
42