You want to account for the time it will take for concrete to cure before faming can start on a construction project. What is the best way to model this on the or

Link the two tasks with a finish-to-finish dependency.

Indicate the break between the links with a modified sltart-to-start-dependency.

Add lag to the dependencies between the two tasks.

Add a new activity that reflects the concrete curing time.