damianfrasieanu3616 damianfrasieanu3616 01-03-2024 Business contestada If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called: a) splitting b) Resource-constrained scheduling c) Resource scheduling d) Resource accommodation e) Resource smoothing