An emergency loan application is received 30 weeks after the designation date, but it was not complete until 4 weeks later, when all the applicant's final yields were determined. The application will be:
A. Processed and approved or rejected within 60 days of the date of a complete application
B. Rejected, because a complete application was not received within 8 months of the designation
C. Considered as an operating loan request