The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows:
Actual Costs Budgeted Costs
Units produced 1,500 1,500
Direct materials cost $5,630 $5,560
Direct labor cost 1,600 1,540
VOH:
Maintenance 735 640
Power 270 200
FOH:
Grounds keeping 1,450 1,400
Depreciation 500 500
Calculate the flexible budget variance.
a.$295U
b.$70F
c.$50F
d.$345U