A project manager needs to alter their budget after making changes to the project schedule and costs. This is necessary in order to _____?
1) re-baseline the budget to track project progress of costs
2) baseline the budget to track project progress of reserves
3) baseline the budget to track project progress of costs
4) re-baseline the budget to track project progress of tasks