contestada

Linda is the project manager of a construction project. The budget for her project is $275,000. The project team made a mistake early in the project that cost $34,000 in added materials. Linda does not believe mistakes will likely happen again because the team is 30 percent complete with the project and things are once again going smoothly. Her sponsor wants to know how much more funding Linda will likely need on the project. What should Linda tell the sponsor?

A. $192,500
B. $241,000
C. $309,000
D. $275,000