Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $49,000, and its expected cash flows would be $11,450 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?
Select the correct answer.
a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0. c. Project L, since the NPVL > NPVS. d. Neither Project S nor L, since each project's NPV < 0.