The main production line at PDQ has a takt time of 48 seconds and has 6 operators with the following cycle times: 36 sec., 42 sec., 15 sec., 22 sec., 46 sec., and 43 sec. Which tool should PDQ use to show the relationship between operator cycle time and takt time?
Line balance chart
Value stream map
Process capacity chart
Standard work sheet