Which of the following is not one of the potential responses to a specific risk event: a. Mitigating b. Retaining
c. Ignoring d. Transferring e. Sharing The most common definition of success within excellent companies is: a. Within time b. Within cost c. At the desired technical/quality level d. Accepted by the customer e. All of the above Lessons learned are BEST completed by: a. The project manager b. The team
c. The sponsor d. The stakeholders Which of the following is believed today to be a major reason for project failures? a. Poor morale b. No employee commitment c. Poor human relations d. No functional commitment
e. All of the above In the early days of project management, the most common definition of success was: a. Did it work? b. Within time c. Within cost
d. Customer satisfaction e. Nonexistent