Meat Deal has developed the following schedule converting old ham and sausage display cases to more environmental ones: week units
1 25
2 40
3 55
4 65
5 60
Historically, the learning rate has been 85 percent on such projects. The budget allows for a maximum of 30 direct labor employee per week and a total of 6000 direct labor hours for entire schedule. Assume 40 work hours per week. If first unit took 70 hours to convert, why is this schedule not feasible? How should it be altered?