You are a production manager. You intend to convert the planned orders to production orders through CO41. However, the command cannot go through and there is a red cross on the planned order. Which one could be the reason?
Group of answer choices
A) You did not run MRP.
B) Raw materials have not been delivered.
C) You run out of cash.
D) There are too many scheduled production orders.