Consider the following set of activities:
Time Predecessor
Activity Required Activities
A 5 None
B 4 A
C 5 B
D 8 B
E 9 C
F 6 C,D
G 8 D
H 3 E,F,G
1Draw the CPM network for this problem.
2Calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities.
3What is the earliest time that the project can be completed?
4.If the project needed to be completed two (Time) earlier, what would you recommend?