Calculate Estimates at Complete (EAC) using Earned Value Management. Question 4 of 9. Given the following data, calculate EAC based on Cumulative Cost Performance Index as the performance factor. Round to the nearest dollar. BAC-1000; BCWS 500; BCWP-400, ACWP-400 ?