For questions 5 and 6, consider a single queue and single server where the four jobs with processing time in days and the due date in days arrive at the work in the order A,B,C,D, to be scheduled.. Question 5. The first job to be scheduled for the FCFS rule is A. How many statements are correct? 01223 (A) For the SPT rule, the first job scheduled is job D (B) For the EDD rule, the first job scheduled is job C (C) For the LPT rule, the first job scheduled is job B Question 6. Diagnostics based on Flow such as Lateness and Utilization are used to evaluate and manage schedules. How many statements are correct? 0123 (A) For the SPT rule, average lateness is 1.8 days, average number of jobs in the system is 2.1jobs/ day, and utilization is 48%. (B) For the EDD rule, average lateness is 1.3 days, average number of jobs in the system is 2.4jobs/ day, and utilization is 42%. (C) For the LPT rule, average lateness is 5.0 days, average number of jobs in the system is 2.9 jobs/day, and utilization is 34%.