Tekan-Tekan Sdn. Bhd. has order for 200 Model AS-120 calculator for delivery on day 200. The calculator consists of three parts. Components 2 and 3 form subassembly 1 . Sub-assembly 1 and component 4 form the final assembly. Following are the work centers and times of each operation. Table Q3(a) shows routine file of the operation. Assuming: - Only one machine is assigned to each operation - The factory works on 8-hour shift, 5 days a week - All parts move in one lot of 200. (a) Illustrate the backward schedule based on the information given above. (12 marks) (b) Identify when component 3 must be started to meet the delivery date. (2 marks)