Using your favorite method or tool (such as forward-pass, listing begin-end paths by hand, MS Project, or whatever else) determine the schedule of the project whose activities, dependencies, and durations (in weeks) are shown in the table below.
Question 31 options:
15 weeks
12 weeks
8 weeks
17 wee