A project manager reviewed a project's financials and determined the following:
• The project has a burn rate of $15,000 per month. • The project has $70,000 left in its budget. • The project team needs six months to complete the remaining work.
Based on the information above, which of the following should the project manager perform FIRST?
А. Update the risk register to show funding will run out prior to completion.
B. Attempt to crash the project schedule to reduce the time to complete.
C. Issue a change control request for additional funds to complete the project.