Look at Project TX55: \[ E S(D)=35, E S(E)=47, \text { and } E S(F)=34 \text {. } \] The duration of activities \( \mathrm{D}, \mathrm{E} \), and \( \mathrm{F} \) are 12,13 , and 15 days, respectively