as part of evm, a project manager is calculating the to-complete performance index (tcpi) based on eac. the data that he has is the budget at completion for the project is $100,000, the earned value for the project is $25,000, the actual costs to date are $40,000 and the estimate at completion is $115,000. what is the tcpi that he will obtain?