Given the following data for the tasks involved in assembling a product, design an assembly line with a cycle time of 10 minutes. Answer the following questions: 1. Draw the precedence Diagram. 2. Assign tasks to stations, greatest number of following tasks. 3. Determine the percentage of the idle time. 4. Compute the rate of output that could be expected for this line assuming a 500-minutes working-day. 5. What is the max. output? 6. What is the min. output? A B C D E F G H J Tasks 5 6 2 4 2 6 2 120 8 Task Time B B& C C D&E E&F G&H Immediate Predecessor