.Montague Composite makes a unit A, which
consists of two units of B, three units of C,
and four units of D. C is composed of three
units of D and two units of E. Items A, C, D
and E have on-hand inventories of 10, 20, 30
and 40 units respectively. Item B has a
scheduled receipt of 50 units in period 1, and
C has a scheduled receipt of 90 units in period
1. Lot-for-lot sizing is used for items A and
B. Item C requires a minimum lot size of 60
units. D and E must be purchased in multiples
of 35 and 55 respectively. Lead times are one
period for items A, B and C, and two periods
for items D and E. The gross requirements for
A are 180 in period 5, and 220 in period 8.
Determine the planned-order releases for all
items using template 2 (provided at the end of
the paper)