Question: There Are Four Activities On The Critical Path. Coincidentally, Their Standard Deviations Are All Equal To 4. The Standard Deviation Of The Critical Path Is Therefore Equal To: 2. 4. 8. 16. 64.
There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to:
2.
4.
8.
16.
64.