A project team is planning to use green power obtained from a separate campus facility through an internal campus agreement. The project team did not use an energy model for EA Credit Optimize Energy Performance. No other buildings on campus obtain power from this facility. What is true about the project's ability to earn EA Credit Green Power and Carbon Offsets?
A. The campus facility that supplies the power does not have to be Green-e Certified
B. The project will be required to purchase RECs
C. At least 70% of the power supplied must be certified, along with a 2-year contract
D. The project building can share the credit with other buildings on campus